The Effluent Force Main installation continued down Toetly Road- had to bypass some power poles with a little help from Kootenai Electric-

In Lift Station 1- the influent pump station by the Lagoons- the slab was poured and wall forming began-



On the main site at Lift Station 2- the effluent pump structure- the sump basin was poured, the slab grade backfilled and a rebar mat was constructed-