Late in the week I had the chance to get some elevated shots in a Genie lift-
the first is the PREM building, 24 foot walls on top of a slab, 18-20 feet of the walls sit below the original site grade. I left the trucks in the upper right corner for perspective-

This is the Treatment Building with half of it being tested for water leaks at the time of picture-

In the meantime the Wetland Discharge Area has seen step-by-step progress- this week the perforated pipe with gate valves was installed. I'll be back soon with Week 20 update!