And began installation the Aero Mod system in earnest. First order of business was a series of vertical piping in the aeration basins-



The suction hoods are staged on the concrete slopes. Some details were taken care of before installation-

Backfill continued around Lift Station 2-

And the main connection to bring water from the existing City of Plummer system down to the WWTP site was put in place-


Even away from the main site we still have to deal with groundwater!