In the end we had our casing in place with a ductile iron section of Effluent Force Main, ready to tie into the system-

At Lift Station-1 a manhole was installed by Owens Construction-


The next phase at the Mechanical building was forming up the stem walls around the UV room. These three shots show some of the progress-



Last week the Operations foundation was filled with fine gravel after the under-slab plumbing and electrical work was finished. Here is the foundation grade covered with visquene ahead of a concrete pour scheduled after Thanksgiving weekend-

An oil-water separator was installed north of the Mechanical building. The first picture is from last week when a hammer was needed to knock some rock out of the way-

Once the hole was deep enough Owens successfully installed the vault. That's all for this holiday-shortened week!