Sitting right in front of Mechanical-

A pretty substantial hunk of metal! (The black lower portion is actually the fuel tank.) -

And now we’re getting serious- in the Belt Press room Challenger begins running rigid conduit to the various control boxes. Here Tom is working on pipes to the Sludge Pump panel-


Here Rick and Brent start work on bringing conduit to the Belt Press panel-


Todd, Challenger Electric, takes a break in the Belt Press room, background, after installing the breaker box in the UV room, near right wall-

By the next day Todd has also installed the step-down transformer near the breaker panel-

And a full view of the Belt Press room to wrap-up the week-