Saturday, July 25, 2009

Week 2- water, PCS and mud...

Well, this is off to a cracking start! John (CNI) is becoming an expert at dewatering, getting plenty of practice with the trench we dug last week. Meanwhile the excavation for the first two buildings began-

Treatment Building (Aeromod basin)-



and Phosphorous Removal Building (PREM-1)-



This is a pattern that we would prefer not to see: dig a hole, find water!

In the meantime Mary Monahan of USKH was large and in charge making sure the PCS was identified and set aside for proper disposal-



"No dice, boys! Take it away!"



Larry Sant of GeoEngineers paid a visit to check the quality of our mud-



"No Larry, the hole on your OTHER right!"



In the meantime, John waved his arms and said the magic words, making the water go away! Unfortunately, over the weekend he forgot the magic words...

No comments:

Post a Comment