Saturday, July 25, 2009

Week 4- pcs, less water, gradual progress...

So this week was transitional- decisions were being made on blasting the rock, we were trying to finish dealing with PCS and the Treatment basin was prepped for structural fill.

The first order of business was making sure the lagoon effluent line was really fixed, which it was-



Somebody got bored...again!...and drove the dozer into what had been a settlement pond-



Brian to the rescue! (They got it out, safe but dirty!)



Mary Monahan came back for one more round of PCS removal-



and we finished the week with a little structural fill-