Week 35, Part 2 Operations and Exterior Progress Views

Over at Operations All Wall placed insulation and vapor barrier in preparation for drywall-



Here are some stacks of drywall waiting to be used-



Insulation in the mechanical room of Operations-



Then the drywall started going up-



Rod Willard, City of Plummer Public Works Director, has a look at progress in the Operations building-



The Mechanical building in progress as seen from the Trail of the Coeur d’Alene’s-



A view from the southwest including Lift Station 2 (effluent)-



At the end of the week we took a ride on a lift and got this overhead shot of Operations-



And this shot of Mechanical with the plywood sheeting in place, ready for “dry-in” (roofing felt). And that’s all for this week!