Outside the Operations building, the City worked with Owens to tap into the potable water line. A hydrant and valve will be installed here-
Later Owens worked on Line G, the gravity sewer line from our plant site which runs back to the Influent Lift Station-
Also, behind the Mechanical building, Owens tied the Reuse Water Tank to the UV discharge line-
The window subcontractor installed all the windows in Operations this week-
Final touches were put on the rebar and grade in the Sludge Basin- the open area at the west end of Mechanical. This is the final area for concrete to be poured in or around the Mechanical building-
And the roofers "dried in" the building by installing felt and ice shield plastic-
To wrap up this week, here's a view from the southwest of the Operations building with Lift Station-2 (effluent) in the foreground. Operations is now ready for insulation and drywall, it will take a couple weeks for the metal roofing to arrive. That's all for this week-