So, we left last week as "getting close" and now the day has arrived- final checks on the details of the wall forms-
The Phosphorous Removal (PREM) hole is not completely ignored but needs a little trim in the northwest corner before rebar can go in-
And now the truck is on site to pour the east wall of the Treatment Building-
"Dennis, I don't see your cell phone and we're not going in to find it!"-
Major reach from the Champion pump truck-
Can't stop tying rebar- another pour just days away-
Next day it's time to strip and move on to the next wall-
Monday, August 31, 2009
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment