So- you've got over 1,000 cubic yards of blast-fractured rock. What do you do next?

Dig-



Scoop-



And more digging-



Until you get it down the the water table-



Empty some of the water and dig some more! Hey, Jason- did you find the bottom yet?




In the meantime Rodbusters got on site and began installing rebar for the Treatment Building slab-





And back at the Phosphorous Removal hole, more fun with water and rocks! This is going to take a while, see where we're at in Week 8-