Friday, August 28, 2009

Week 9- Base Rock and Vertical Iron

Good progress this week in the Phosphorous Removal hole. Got the subgrade rock in, placed fabric and installed the bedding. Here you can see how to get a rubber-tire roller out of a 20' hole!







By the end of the week we had initial wood forms lowered into the hole, ready to set up a carpentry shop and build stuff!




In the meantime at the Treatment Building the next step after slab pour was to get more vertical rebar in place and construct forms on the east side for the first wall pour-

















By the end of the week- getting close!