Wednesday, September 2, 2009

Week 13 Part 1- PREM south wall and access road-

It's time to mention some names that are doing all this work! During this phase from Week 13 to Week 16 or 17 (to be determined) the main form crew in the PREM hole has been Kevin Brown with Joel, Merle, Scott and Phil. Crews are not fixed all the time, people have to be flexible (or at least quick if Dennis is nearby!) but these are the general assignments. In the Treatment Building we have John Gabbard with Dennis, Rick, Roger, Robert, Ross, and Orion. We'll get all the last names and some pictures in before the end!

Here's a few interesting views of the PREM hole and Treatment building from the carpentry perspective-









Here is the early stage of buttress installation- the crane flying in the steel, setting it just right and a look at the couplers-







Here's a long vertical view of a rebar curtain being placed on the south PREM wall-



Owens Construction recently removed some unsuitable material from the main access road and rebuilt it with stronger stuff-