Wednesday, September 9, 2009

Week 14, Part 1- Rebar wrap-up, another pour ahead...

In the early part of Week 14 the rebar crew, Rodbusters, wrapped up their work on site for now. They've been done with the Treatment building for a while and needed to complete work on the north half of the PREM building-









In the meantime we were ready to begin leak testing the tanks in the Treatment building. Here's a water hose being helped up to one of the north wall tanks with some lengths of pipe!-



On the south side of the Treatment building the outer wall is being formed up. The first shot shows cam locks in the plywood- these hold the horizontal 2x4's that you see in the 2nd picture-





Form building on the south half of the PREM building continued- the first two 8 foot levels of plywood were installed and supporting 2x4's were attached (horizontal "walers" and vertical "strongbacks")-






No comments:

Post a Comment