Tuesday, October 13, 2009

Week 18, PREM final pour, Force Main and Lift Stations

This week saw the project expand into three separate areas of work which made the inspector actually break a sweat keeping up! Well..., not really...

But this week began a very busy period which continues to the day of this post and beyond. The Force Main has been much anticipated and finally got underway this week-






Jason & Don bolt up a fitting in one of the Pressure Cleanout manholes-





We had to go under the Highway 5 bridge to St. Maries-






Third day into it we hit bad weather-



And somewhere along the way we found an unmarked culvert- the new public works director for City of Plummer, Rod Willard, got a close look just to be sure!-



Along with the Force Main, the Lift Stations (Influent and Effluent) continued to move along.

Lift Station 1 (Influent by the Lagoons) was further along and ready for slab rebar-




Lift Station 2 (Effluent, on the main site) needed more adjustments so the bedding was still being placed- (after this picture look for Part 2 which will be posted above this entry)