Wednesday, January 13, 2010

Week 30, Part 2- Snow and Operations roof

The snow was a nice change, given the other option (mud). Challenger continued to work in the Blower Room tent. This conduit sweep assembly is the beginnings of the Motor Control Center-





Owens backfilled the interior of the Mechanical building-





Back at the Operations building the truss installation was finished in two days-



Next on the 4-day week agenda- glue-lams!







That concludes Week 30 and brings us to Christmas weekend. The week between Christmas and New Year’s and the first full week in January are close behind. That will bring us up to the current week. Things have been quite busy on the interior of Operations and the CMU walls are going up at Mechanical so I look forward to sharing the most up-to-date pictures here soon!