Friday, January 15, 2010

Week 32, Part 1

New Year’s Day weekend brought some nasty weather- rain and high winds. So we arrived on site to fund some work from last week had been undone-



The CNI crew spent an hour or so pulling the visquene tent off some collapsed scaffolding-



Dewatering efforts were resumed in some areas-



Fortunately, since the Operations roof was complete by the end of last week that work zone was open for business-



CNI began framing up a shear wall between the Screen room and the Maintenance/Storage room-



After a few hours CNI and R&R Masonry had the tent back up over Mechanical-



Block laying began in earnest-



In one day we made a lot of progress towards the first lift. One lift of CMU is six courses of 8” block; a four-foot high wall segment-





Challenger Electric still had some work to do in Mechanical. Now they simply have to share the working space with the masons! This is the same area they covered with a small tent last week. They are still under a tent but it’s about 20’ overhead!



At Operations ACI, the mechanical/HVAC sub, began ductwork installation-



CNI continued work on the shear wall frame-



And outside we got a little reminder of the season-