Speaking of the shallow trench we saw Owens' crew digging in the last installment, here is Todd of Challenger Electric trying to figure out what goes where-
And this is why you need to be patient as an electrician! We don't want to flip on a light switch and have the Belt/Filter Press start up in the next building!-
A major duct back will run from the Operations building to the Mechanical building. The installation process begins between Operations and the Treatment structure-
In the UV Disinfection Room (Mechanical Building) the welder installed the handrails leading to the UV floor-
In the Maintenance/Storage room of Operations, All Wall began sanding the finished drywall prior to painting-
After the concrete cured, the wall surrounding the Sludge Basin was covered with a welded metal liner-
And the roof began taking shape on Operations-
Finally, the PREM roof supports were put in place and another week is in the books!
(This roof is actually flat, the bending is part of the panoramic view process! I will get a true, flat picture posted later...)