Friday, March 12, 2010

Week 38, Part 1- Building details, electrical progress

This week saw further progress at both Operations and Mechanical. The metal roof at Operations continued-



Every Monday we have a Construction Progress Meeting. After these meetings Alan Gay the Project Engineer from USKH visits the site and various City of Plummer personnel also check on progress. Here, Mayor Tim checks out a valve at the Effluent Lift Station with Engineer Alan-



And Alan reviews initial progress of the main duct bank behind Operations-



The welder continues to install panels around the Sludge Basin at Mechanical-



The CNI crew is handling most of the equipment assembly and building trim details. Here two crew members are installing doors in the Mechanical building-



By mid-week Challenger Electric was extending the duct bank past the edge of the Treatment structure and towards the Mechanical building down grade to the west-



So many pipes, so little time!



And the UV equipment started to roll in-



Here CNI places the UV disinfection troughs onto the lower floor of the UV basin and positions them for permanent installation-