As a part of the exterior finish on both Operations and Mechanical a product called Hardie Plank is being installed under the gables of both buildings-
In case you thought the bluest skies you’ve ever seen are in Seattle, well, they’re actually in Plummer, ID! (This picture has not been tested for Photoshop steroids yet…) Here’s a progress view of Mechanical from the southeast corner, still plenty of roof to install-
In the Office room of the Operations building some critical control panels have been installed-
And finally we pour the Chemical Storage containment pad- (they didn’t have any blue skies available this day)
The Belt/Filter Press room is done with the primer coat-
This is the UV room with a still-wet primer coat-
The Hardie Plank installation continues on Mechanical's south wall-
Electrical had to take a hard right turn at the PREM structure to route power for lights and a pump-
And finally in UV the trim is being primed before installation. That's all this week and we are almost up to date!