From last week we still have roofing materials on site while the metal roof on the Mechanical building is wrapped up-
The containment walls for the Chemical Storage pad were poured early in the week-
By mid-week CNI’s crew put a smooth finish on the upper portion of the wall. Only a foot or so will be above grade after fill is put in for the access road that runs adjacent to the Chem Storage pad-
North of Operations the structural fill was placed and compacted-
Then fine gravel for a sidewalk grade and forms were built-
And finally the concrete pour for the Operations building sidewalk and driveway entrance (into the Maintenance/Storage room)-
John Gabbard of CNI is the one-man finishing crew for now-
The finished product speaks for itself! -