Week 44, Part 1

From last week we still have roofing materials on site while the metal roof on the Mechanical building is wrapped up-



The containment walls for the Chemical Storage pad were poured early in the week-





By mid-week CNI’s crew put a smooth finish on the upper portion of the wall. Only a foot or so will be above grade after fill is put in for the access road that runs adjacent to the Chem Storage pad-



North of Operations the structural fill was placed and compacted-



Then fine gravel for a sidewalk grade and forms were built-



And finally the concrete pour for the Operations building sidewalk and driveway entrance (into the Maintenance/Storage room)-



John Gabbard of CNI is the one-man finishing crew for now-



The finished product speaks for itself! -