And the electrical ramp-up continues- the Generator was delivered by mid-week-



Sitting right in front of Mechanical-



A pretty substantial hunk of metal! (The black lower portion is actually the fuel tank.) -



And now we’re getting serious- in the Belt Press room Challenger begins running rigid conduit to the various control boxes. Here Tom is working on pipes to the Sludge Pump panel-





Here Rick and Brent start work on bringing conduit to the Belt Press panel-





Todd, Challenger Electric, takes a break in the Belt Press room, background, after installing the breaker box in the UV room, near right wall-



By the next day Todd has also installed the step-down transformer near the breaker panel-



And a full view of the Belt Press room to wrap-up the week-