Friday, December 4, 2009

Week 23, Part 2- Tank-1 and Treatment Building misc.

Near Lift Station-2- the point from which we pump the treated water off site- there are two other structures- Tank 1 and Vault 4. It turns out that Tank 1 sits so low that we needed to hammer out some more rock. Poor KC sat on the hammer for 2-3 days getting it down to grade!





Once the hole was low enough, Owens Construction was able to install the manhole for Tank-1 -







Over at the Treatment building a couple details were taking shape. The catwalk and handrail system was worked on-





Also the support wall for stairs on the north side was formed up-





Hmm, it's only foggy most mornings- here's the same shot 5 hours later!

No comments:

Post a Comment