Tuesday, December 29, 2009

Week 29, Part 1- Static Screens and Aero Mod System

Editorial note- this post was originally labeled as "Week 28". This was a mistake and a new post will be published that covers the REAL Week 28!

This week the Static Screens were set in place on concrete pads. This is the first process that the incoming Waste Water goes through as it enters the plant.

Here is the sequence for form building and pouring one of the pads close-up-







And a wider view of the pair of pads and screen units being prepared and set in place-







And let's pull out the measuring tape just to make sure!



One of those rare blue sky days, a view of the Operations Building before work starts on the roof-



Work continues in the Treatment Building, installing piping and valves for the Aero Mod aeration system-







Here we have a few wide shots of the site in the snow. You can click on these individually to see them in better detail in your browser- (hit the back button inbetween views)