While construction of the new Treatment Plant occurs, the old lagoon system is still operating. On a frosty, foggy morning it actually looks interesting...well to some people anyway-
This week the electricians finished rough-in work at the Mechanical building-
And we were able to do the stem wall concrete pour on a nice afternoon!
At the Operations building we poured in the floor slab-
This looks so much better than gravel and mess of conduit spaghetti!
The next day we were ready to set door frames and move right into CMU wall installation-
Here's the first corner being put in place. (Southeast, for the curious) All four corners were worked on simultaneously but this guy got his blocks in first!